Archive | Parking

Lower Ground Floor

Good progress is being made on all the basement levels and on the new Link building. The opening between the basement parking and the new parking in the Link building is the next big milestone. To assist the contractor in positioning required scaffolding for this event, Standard Bank’s access to their Despatch area has been […]

Continue Reading

Parking update – 10 November

Work in the basement parking areas are progressing well. There will be a phased handover of parking bays from the end of November. Samantha Lambert of Redefine will inform relevant parkers. The current parking areas under the towers will be redecorated. P3 will be washed down and painted after hours for completion by 13 December […]

Continue Reading